Essence of the Project: technical audit of documentation for the construction of a 250 MW wind power plant in Chaplinsky district of the Kherson region.
Works executed by IKNET:
- Audit of existing documents that are necessary to determine the cost of wind power generation electric power 250 MW;
- assessment of the risks of limiting the output capacity of wind power plants (technical and legal), taking into account perspective objects of the RES of the district;
- evaluation of the connecting cost;
- Impact of the approved scheme of connection on the cost of connection, the risks of cost increase are investigated.