Project description: implementation of the scheme for the long-term development of 20 (35) kV and above for the period from 2023 to 2032 at DTEK DNEPR ELECTRONIC NETWORKS JSC.
Works performed by IKNET:
- forecasting the levels of electricity consumption and load for winter and summer for the period 2022-2032;
- actual and prospective volumes of electricity generated by generating facilities were determined;
- analysis of the existing state of substations, the need to replace switching equipment, and transformers;
- calculation of the operation modes of the power grid in normal and repair modes until 2032;
- development and substantiation of proposals for new construction, reconstruction, and technical re-equipment of DTEK DNEPR ELECTRONIC NETWORKS JSC;
- forecasting the levels of technological electricity consumption;
- calculation of short-circuit currents;
- calculation and assessment of the need to install compensating devices at substations;
- analysis of power and electricity balances;
- assessment of investments required for the development and reconstruction of networks, ranking of objects by the term of implementation;
- developed a scheme of electrical connections of 35-150 kV normal mode grids for 2027 and 2032.