Essence of the Project: biomass power plant construction on waste wood near the railway station Romankivtsi, Sokyryany district of Chernivtsi region.
Works executed by IKNET:
designed analytical report "The calculation of the predicted financial and economic indicators of the project on electricity and thermal supplied power by the station".
As part of the analytical report, executed the following:
- analyzed of raw materials, which may using on the station;
- designed indicative technological scheme of work plant, logistics;
- designed the scheme of electric power issuing by the station in the external electrical network;
- performed the determination of conditions of electricity and heat selling by the current laws of Ukraine;
- defined predicted financial and economic indicators of the project.
Based on the designed analytical report, offered optimal solution on the concept of the project.