Land plot of 20,24 hectares is located in Shpolyansky district Cherkasy region with the possibility of SPP construction, capacity of 9,8 MW.
Geographical location of the land plot for SPP construction in Cherkassy region
Nowadays, the following documents on the project is obtained:
- business model of the project is developed;
- City planning conditions and restrictions of land plot building;
- Agreement on 20,2394 ha land plot lease;
- FS "Capacity output chart of solar power plant (SPP) with capacity of 9,8 MW on the territory of Shpolyansky district Cherkasy region" is designed;
- FS is approved by PJSC "Cherkasyoblenergo" and Central Energy Systems of NPC "Ukrenergo";
- design and survey work on the SPP construction territoty is executed (geology and geodesy);
- TS for grid connection of SPP obtained in PJSC "Cherkasyoblenergo";
- TS on electricity supply of SPP own needs from power grids PJSC "Cherkasyoblenergo" is obtained;
- Design "Capacity output chart of solar power plant (SPP) with capacity of 9,8 MW on the territory of Shpolyansky district Cherkasy region" is developed;
- Declaration of the beginning of construction work is registered in DABI Cherkasy region;
- commercial proposals from a number of leading European companies for the solar power plant construction of "turnkey" is obtained.