The construction of a ground-based solar power plant with a capacity of 9.8 MW near the settlement Olshanka of the Kirovograd region.
Works executed by IKNET:
- developed business model of the project;
- developed the Feasibility Study "Scheme of power output of a solar power plant with a capacity of 9.8 MW near Olshanka settlement in the Kirovograd region";
- obtained appropriate agreements of Feasibility Studiy with PJSC "Kirovogradoblenergo" and Dnipro POwer System of NEC "Ukrenergo";
- obtained the Technical Requirements for connecting of the SPP to the electricity grids from PJSC "Kirovogradoblenergo";
- the Technical Requirements agreed in the Dnipro Power System of NEC "Ukrenergo".