Project description: implementation of a 100 MW WPP project in the Odessa region.
Scope of IKNET: Customer's technical consultant:
- analysis of design decisions on compliance with regulatory requirements and optimization of investments by:
- cable lines for collecting power of the 35 kV facility;
- 110/35 kV substation and 110 kV transmission line to the connection point;
- ASCME (automated system of control and metering of energy resources) project;
- SCADA WPP system;
- control of construction and installation works of the electrical part of the object.